Project Detail
Contract Type
Engineering,
Procurement & Construction
Location
Maroun & Omidieh, Iran
Executive Status
Contract Termination
Physical Progress
50%
Commencement Date
Dec., 10, 2002
Initial Duration
18 months
Brief Description &
Technical Specification
The project includes two concrete tanks with a capacity of one million barrels and two concrete tanks with a capacity of 500 thousand barrels. Due to strict requirements on waterproofing the tanks regarding the environmental aspects, the tanks was designed and built using sliding formwork system to prevent the fuel penetration into the nature. Maroun-Omidieh strategic oil
tanks are the first and the only.
General works’ Quantity
concrete ones in Iran.
Earth works 2,500,000 m3
Concreting 75,000 m3
Reinforcement 14,000 tons
Formworking 8,000 m2
Sliding formwork 75,000 m2