Concrete Fuel Tanks of Mofatteh Power Plant

Client Iran Power Development Company
Location Hamedan, Iran
Scope Of Work Engineering, Procurement, Construction (EPC)

Project Detail

Contract Type

Engineering,

Procurement & Construction

Location

Hamedan, Iran

Executive Status

Final Handover

Physical Progress

100%

Commencement Date

Mar., 12, 2009

Initial Duration

30 months

 

Brief Description &

Technical Specification

Bolandpayeh service in this project is to design and build a standby buried Mazut tank with the capacity of sixty thousand cubic meters for the emergency situation of the plant. The tank has

a cubic shape which consists of 4 equal parts.The foundation has a squareshape with the side length of 105 meters. The thickness of the foundation beneath the columns is 60 centimeters and in the other area is 40 centimeters. The height of the walls and columns are 7 meters. The thickness of the walls at the base is 60 centimeters and changes to the top of the wall by 40 centimeters.The tank has 224 columns with a diameter of 1 meter. The full operative height of mazut in the tank is 6 meters.

 

General works’ Quantity

Earth works 300,000 m³

Concreting 22,000 m³

Reinforcement 3,000 tons

Formworking 38,000 m²

The roof was executed using precast members. There are some corbels elements act as upport of the precast members. After execution of the beams in cast, the precast members were installed and the final concrete cover was poured consequently. A group of shear key elements

was considered in the precast members to merge performance of the precast members and the

final concrete cover. The final level of the roof is about one meter higher than