Kermanshah Burn-injury Hospital

Client Kermanshah University of Medical Sciences
Location Kermanshah, Iran
Scope Of Work Construction (C)

Project Detail

 Contract Type
Construction
Location
Kermanshah, Iran
Executive status
Initial Handover
Physical progress
100%
Commencement Date
Oct., 2, 2013
Initial Duration
18 months 
Brief Description & Technical Specification 
Golestan Hospital was designed for the purpose of Burn-Injury with a capacity of 50 beds. The Hospital is considered as a part of nearby Imam Reza Specialized Hospital with the capacity of 600 beds and the “University of Medical Science of Kermanshah”. The total area of Golestan Burn-Injury Hospital is 8,000 thousand square meters which was designed in 5 levels. The hospital has 22 beds for burn-injury purpose, 11 BICU beds, 8 restoration beds and 9 beds for infectious purpose. The hospital has 2 operation rooms.
General works’ Quantity
Earth works 24,000 m³
Concreting 3,000 m³
Reinforcement 250 tons
Formworking 10,000 m²
Metal works 1,000 tons