Client Petrochemical Industries Development Management Co.
Location Asaluyeh, Iran
Scope Of Work Construction (C)
Project Detail
Contract Type
Construction
Location
Asalouyeh, Iran
Executive Status
Final Handover
Physical Progress
100%
Commencement Date
Aug., 01, 2004
Initial Duration
10 months
Brief Description &
Technical Specification
Bolandpayeh service in this project is to implement the Ammonia-Urea Complex of Asalouyeh which includes all concrete and steel structures and also all equipment halls and relevant infrastructure facilities.
Moreover the machinery and equipment foundation was constructed accordingly.
General works’ Quantity
Concreting 40,000 m³
Reinforcement 3,500 tons
Formworking 75,000 m²
Metal works 2,000 tons